GMP in pharmaceutical production and pest control

At a glance
GMP aims to prevent product contamination; preventing pest entry is a facility requirement.
Who is subject to it or asks for it?
Pharmaceutical and medical product manufacturers, depots and medical device makers.
What it expects from pest control
Facility controls that prevent pest entry; assessment of method and chemical impact on product safety.
What does the auditor ask for?
- Pest control procedure
- Contamination risk assessment of biocidal products used
- Change control
- Service records
How Pak İş IPM and PMDP meet it
Pak İş builds the programme on IPM: survey and risk analysis, station and monitor placement plan, periodic service and trend review. Service records, the station map and related documents are kept in the PMDP customer portal and can be shown at audit. This is not a guarantee of an audit result; the result depends on the site’s own system, hygiene practice and the certification body’s assessment.
Records: what will you show?
- Service report: date, time, applicator, area and action taken
- Station/monitor map and numbered station list
- Activity counts and trend chart
- Product label, safety data sheet and permit information
- Corrective action: finding, root cause, action, owner and closure date
The backbone of the programme: the IPM cycle
- Survey and risk analysis
- Exclusion
- Source removal
- Monitoring and counting
- Trend and threshold
- Targeted intervention
- Verification and root cause
Common mistakes
- Treating a one-off treatment as a programme: without monitoring and trend there is no system evidence.
- Keeping records scattered: on audit day documents cannot be found and closure evidence is missing.
- Expecting treatment to fix entry and hygiene problems such as open doors, waste and damp.
- Not checking whether the standard version and customer requirement are current.
Important note
This page is general information, not legal or certification advice. Standards and regulations are updated; consult the official text and your certification body for current requirements.
Frequently asked questions
Can baits be used in a GMP site?
Depends on area class and risk assessment; baits are avoided in production areas in favour of mechanical and monitoring methods.
Why is change control important?
A new product or method can change contamination risk, so quality unit approval is needed.
How does Pak İş help?
Survey and risk analysis, an IPM-based programme, station maps, service reports and records kept traceable in the PMDP portal; no audit result is guaranteed.